Picture a contractor whose crew reaches a client's gate with the vehicle loaded and the programme waiting. One fitter's height certificate lapsed last week, and the only person who tracks such dates is on leave. The owner learns about it from the client.
In energy and utilities: what should the owner set up first in HR?
Set up a single register of people, authorisations and expiry dates, then control who may enter each site, including contractor workers. Next come clear roles, shift rosters, written employment terms and a safety incident routine. Hiring plans, pay grades and skill building follow once you trust the records underneath them.
Why permission comes before everything else
In an office, a missing HR file is an inconvenience. In solar construction, power contracting, quarrying, oil and gas work or a treatment plant, it can stop a crew, put an unqualified person on live equipment or leave you unable to show a client who was where. Your first HR system therefore answers three questions on any morning: who is working, where, and what are they allowed to do. A shared spreadsheet kept carefully is enough to begin. Separate files for every location are not, because the same technician moves between them and the dates drift apart.
The order that works
- 1
Build the people and permissions register
List employees and contractor workers who enter your sites. Record role, base, certificates, authorisations, medical fitness where required, expiry dates and where the evidence is filed. Name one keeper and a deputy.
- 2
Set the gate rule
Decide that nobody is rostered for a task unless the register shows current permission. Say who may refuse, who may not override, and how an urgent breakdown is handled without breaking the rule.
- 3
Bring contractor records in line
Agree what each contractor must send before a worker arrives: identity, competence evidence, induction and an emergency contact. Check it against who actually signed in. Their employment stays with them; your site risk stays with you.
- 4
Write down roles and authority
For each role, state the main work, the permits it may hold, who it reports to and who covers it. Separate a technician who assists from one who isolates, and a plant operator from a shift lead.
- 5
Put rosters and attendance on one pattern
Use the same codes at every location for shift, travel, standby, call-out, leave and overtime, with a supervisor confirming them. Whoever prepares pay should receive one agreed input, not a pile of messages.
- 6
Complete employment terms and files
Every employee needs written terms, site mobility and travel expectations, notice, allowance rules and a file you can find. Have your adviser check the wording.
- 7
Close the loop on incidents and concerns
Give workers a plain way to report near misses and raise complaints, name who responds and record what was done.
One row per person
Name:
Employee or contractor:
Employer if contractor:
Role:
Home base:
Current site:
Certificate or permit:
Issued by:
Expires on:
Evidence filed at:
Allowed to work alone: Y/N
May issue permits: Y/N
Renewal booked on:
Keeper:
Last checked on:Keep one line per certificate if a person holds several, so a lapse cannot hide behind a valid one. Review upcoming expiries on a fixed weekly or monthly day, and compare them with the project programme. A renewal that clashes with a mobilisation is a planning problem you want to see early.
Decide who is allowed to decide
Records do little unless people know who acts on them. Write a half page naming who may approve a hire, add a person to the roster, authorise overtime, refuse a gate entry, stop a task and change someone's pay. In a growing contractor these decisions drift to the owner by default, and sites then wait for a phone call. Give supervisors the routine calls with clear limits, and keep exceptions, new roles and pay changes at the top.
Brief supervisors in a working session using real cases: a technician asking for leave during a shutdown, a contractor worker arriving without evidence, an operator reporting that they are too tired to continue. Their answers show which rules are unclear. Rewrite those first, and put the short version where crews will see it, in the site cabin, control room or vehicle file.
Add hiring and pay once the base holds
With permissions and rosters visible, you can see which roles are thin and which project dates carry risk. That gives hiring a plan: roles needed, authorisations required, and the date by which each person must be inducted. It also shows who has taken on higher duties without any change in grade, which is where pay work should begin. A salary exercise started before this ends up pricing job titles that describe nobody accurately.
What can wait
- A formal appraisal cycle with ratings, until supervisors hold regular short conversations about real work
- A thick handbook, beyond the few rules people need on attendance, conduct, safety, travel and leave
- A detailed competency framework for every role; start with the ones where one absence stops work
- New HR software, until you know which fields, codes and approvals you actually use
- Engagement surveys, while basic problems such as late travel arrangements or unclear overtime are already known
Where owners go wrong
The first mistake is giving the register to someone with no authority to hold back a deployment. The dates are then accurate and ignored. The second is letting each project manager keep a private version. The third is treating safety paperwork as separate from HR, so induction records and employment records disagree about who started when. Pick one source, let others view it, and correct it only through the keeper.
Test the setup with a simple exercise. Choose a site and a date next week, then ask for the names, permissions and cover for that shift. If the answer needs several phone calls, go back to the register and rosters before adding anything new.
Repeat the exercise for a night shift, a remote location and a contractor crew. Each can expose a different gap: stale contact numbers, permissions held only on paper at the site, or workers nobody recorded. Give every gap an owner and check it again after the next mobilisation.
Where to go next
Start the register this week with one site, then widen it. Our overview of HR for energy and utilities sets out the wider picture, employee records setup covers the files, and an HR audit shows which gaps to close first. You can also tell us your requirements.