Module laying at a ground-mounted plant is nearly done and the client has fixed the inspection date. Your best site engineer asks where they will go next month. The project head says something is coming, sales says the order is still under negotiation, and the engineer starts returning a competitor's calls.
Where does each engineer go when a solar site is handed over?
Keep one rolling view of projects and people: who is on each site, when they can realistically be released, which confirmed and likely orders need them, and who has spoken to them. Review it monthly with sales and project leads. Give each engineer and supervisor a next step, or an honest statement of uncertainty, well before handover.
Staffing each project as it is won treats the team as belonging to that site. The result is idle salary after one handover and a scramble before the next mobilisation, with the same trusted managers dragged from crisis to crisis. Planning across projects is a leadership habit that needs a sheet and a fixed meeting, not a system. The project head, the sales lead and whoever handles people matters should all attend, and the owner should settle clashes in the room.
Draw the board
One row per person in a role that is hard to replace: project managers, site engineers, supervisors, commissioning engineers, senior DC and electrical technicians and safety officers. Columns show the coming months. Installer gangs from sub-contractors are planned separately, by capacity.
Name:
Role and grade:
Current site:
Planned handover:
Earliest release (realistic):
Snag and commissioning tail:
Next project:
Certainty: firm / likely / open
Mobilisation date:
Safety cards expire:
Location limits or preference:
Backup if the order slips:
Told by whom, on:
Next review:Release is not the same as the contract handover date. Allow for civil snags, grid connection waits, testing, documentation and client punch lists. An engineer shown as free too early gets promised to two places. Ask the site manager what must be true on the ground before each person can leave, and write that condition beside the date.
Run the monthly review
- 1
Update the dates
Each project manager revises handover and release dates the day before, with the reason for any slip: land, material, grid, weather or client.
- 2
Grade the pipeline
Sales marks each coming order firm, likely or open, with the evidence. A verbal assurance is not firm.
- 3
Match people to work
Fill firm projects first. For likely ones, pencil a name and a backup. Look for clashes and for people with nothing after release.
- 4
Check the overloaded few
Count the difficult sites carried by the same managers. Assign a deputy who will lead the next one with their support.
- 5
Choose what fills the gaps
Operations and maintenance visits, design review, quality audits on other sites, training on storage or protection systems, leave that has built up, or planned temporary internal assignments.
- 6
Name who tells whom
Every person due for release within the notice window you set gets a conversation with a named manager, who records it.
Hand over the site without losing the team early
The final weeks of a project are when people are tempted to leave and when their memory matters a great deal. Plan the closing team by task: punch list, testing, drawings as built, stores reconciliation, client training and demobilisation. Name who stays for each and release others in stages. An installer supervisor can be free well before the commissioning engineer, and the board should show that.
Give the person staying to the end a clear finish line and a stated next step. Where the next site needs them before closure is complete, agree who takes over the remaining items, hold a handover on site and tell the client. Splitting one engineer across two distant sites by phone leaves both poorly served, so record it as a risk with an end date if you accept it.
When a good engineer does resign during closure, ask whether the cause was the next posting, the last one, the allowance or the manager, and note it beside the project. Over several handovers the pattern shows which promises the company is failing to keep.
What to say when the order is not signed
Engineers can accept uncertainty better than silence. Say what is firm, what is being negotiated, when you will know more and what they will do if it slips. Do not promise a posting to hold someone through commissioning. Once a promise breaks, the next one carries no weight in the site camp.
- Ask early about distance, family commitments and the kind of work each person wants next.
- Offer a spell nearer home or at head office after a long remote posting, where the work allows.
- Agree what happens to pay and allowances during a gap before a gap occurs.
- Ask for site knowledge before release: as-built changes, vendor contacts, gang performance and client concerns.
Next, one posting and allowance rule
Redeployment fails when each move is bargained afresh. Write, on one or two pages, which allowance applies by site type, distance and role, what accommodation and travel the company provides, notice before a posting, home visit frequency and who may approve an exception. Share it before people compare notes in camp, and fold existing special deals into it with care.
Then the certificate and card register
A planned move is useless if the person cannot enter the next site. Record work at height, electrical authorisation, first aid and client-specific passes with expiry dates, and show them on the board. Book renewals into the gap between projects. For sub-contractor gangs, require the same evidence before mobilisation and rate each gang at closure on quality and safe conduct, so the next call goes to those who earned it.
What can wait
Workforce planning software, a full grade ladder for every function and long-range headcount models can come after several monthly reviews have run on the sheet. A short ladder for site engineers is the first of these worth drafting, since people between projects ask what comes next for them as well as where. Read more on HR strategy and workforce planning, or about HR for solar EPC companies.
Where to go next
This week, write every engineer and supervisor against a realistic release date and circle those with nothing after it. Speak to the earliest one first. If you want help setting up the review, posting rule and role ladder, tell us your requirements with your project mix and team shape.