Two pipe fitters are testing a riser on the fourth floor. Over lunch one learns that the other, hired in a hurry for a different site last season, earns a clearly higher day rate. By evening the first has taken a call from a rival with a steady project, and two helpers are asking what that call was about.
What should an MEP contractor fix first when rates differ across sites?
Fix the basis of pay before the amounts. Record who is on a day rate, who is paid on measured quantity and why. Then define a small set of grades for each trade by what a person can do unaided, and give each grade a rate band. Place everyone, explain the placing and plan how the odd cases will close.
Differences of this kind are rarely planned. A gang leader quoted a figure when a handover date was close. An electrician stayed after asking for more. A crew moved from a measured work site to a day rate site and kept whichever suited them. Each decision made sense on the day. Together they form a pay system that nobody can explain, run by a site engineer who is also chasing drawings and material.
Start with one honest list
Before any meeting about pay, pull the facts from wage sheets, billing and gang leaders into a single table. For each electrician, fitter, ducting technician, sprinkler installer and helper, note the site, trade, current rate, pay basis, allowances, advances, who agreed the rate and when. Mark entries that exist only as a gang leader's word. That mark alone shows where the next argument will come from.
Then sort by trade and look for pairs: similar skill, similar work, different money. Ask the site engineer whether there is a real reason, such as a licence, a testing duty or leading a small crew. A real reason belongs in the grade definition. A reason that amounts to timing belongs on the list of cases to close.
Grades that a site engineer can judge
Grades fail when they rest on years served or on adjectives such as good and very good. Describe what the person does without someone standing over them. Here is an electrical ladder to adapt; plumbing, HVAC and fire fighting each need their own version.
- Helper: carries, chases walls, pulls cable under direction and keeps tools
- Assistant electrician: fixes conduit and boxes to a marked layout, with checks
- Electrician: wires and terminates from a drawing, tests circuits and reports faults
- Senior electrician: terminates panels, reads revisions and corrects others' work
- Chargehand: sets out the day for a crew, requests material and records progress
Test the wording with your longest-serving foremen. If two of them would place the same person differently, the description is still too loose. Where a task needs a permit or licence under local rules, state it in the grade, and check expiry dates when someone is assigned.
Name:
Trade:
Current site:
Gang leader, if any:
Pay basis: day / measured
Current rate:
Grade agreed:
Tasks seen done unaided:
Assessed by:
Band for this grade:
Position: below / in / above
Plan if below or above:
Told to worker on:
Next grade needs:
Review date:Write the rule for measured work, idle time and moves
- 1
Say which work is measured
Cable laying or repeat duct runs lend themselves to quantity. Panel termination, testing and fault finding reward care, so a day rate with a quality check suits them better.
- 2
Define a payable quantity
State who measures, when, in front of whom, and whether rework or a failed pressure test is paid. Agree it before the first metre is installed.
- 3
Decide idle day pay
When civil work is late or a floor is not clear, say what each pay basis receives, who records the stoppage and whether the crew can be moved instead.
- 4
Protect the rate on transfer
A move sends a note with the person: new site, start date, rate, basis, travel and who to report to. A phone call can start the move only if the note follows that day.
- 5
Name who can change a rate
Site engineers propose and one named manager approves. Verbal promises made to stop a resignation are what created the spread in the first place.
Close the gaps without losing a crew
Do not cut anyone's rate to make a table tidy. Hold the higher figure, say it sits above the band, and let the band catch up or the person move up a grade. Raise those below the band in steps you can fund, with dates you control. Tell each person privately where they stand and what the next grade requires.
Expect the question about the colleague on the other site. Answer with the grade description rather than the colleague's pay. If you cannot answer that way, you have found a case that is not yet closed, and saying so with a review date is better than inventing a reason. Compensation and rewards strategy goes further into bands, allowances and how decisions get approved.
Two things to set up after the bands
The first is the site-wise people record: each site, each person by trade and grade, and moves as they happen. With it, the owner sees where a rival's approach would hurt, and which site has no chargehand. The second is a short induction card that travels with your own people, covering your rules on isolation, hot work, shafts and ceiling access, on top of whatever each main contractor delivers at its gate.
A large bonus scheme can wait. So can software that prices every task. Pay linked to quantity on top of an unclear base encourages people to leave joints untested and cable ends unlabelled, and the commissioning week is where that bill arrives.
When the main contractor's programme slips
Idle days test the rule harder than busy ones. Suppose civil work on a basement is late and your cabling crew arrives to wet walls. The foreman records the time, the reason and who was told at the main contractor. The site engineer then chooses in a set order: move the crew to another floor, move them to another site with a transfer note, or stand them down on the terms already written. Keep these entries with the billing file. They support any claim your contract allows, and they show fitters that waiting time was counted rather than forgotten. Review them monthly to see which clients leave your crews standing.
Where to go next
Compare two fitters of similar skill on different sites this week and write down why their rates differ. The page on HR for MEP contractors sets the pay question beside transfers and supervision, and you can share your requirements if you want help building grades and bands.