Consider a week before sowing when a sales engineer has told three farmers their drip lines will be running by Friday. There are two gangs, one trencher is waiting for a part, and the crew leader on the first farm is about to cover the joints without testing because the next farmer keeps phoning.
How do you stop sowing dates from overrunning your installation gangs?
Work backwards from planting. Estimate crew days for every open order, subtract the days lost to travel, rain, rework and rest, and release only dates the remainder can carry. Give one planner authority over the board, protect testing time on each farm, and decide early which extra hands you will bring in and who supervises them.
The shortage starts in the sales conversation
Farmers order late, and a seller keen to close says yes. The promise is made before anyone has checked field size, water source, trenching conditions, material stock or which crew is free. By the time the schedule is drawn up it is a list of dates already given away. The gang then absorbs the difference through longer days and shortcuts, and the faults come back as service calls in the weeks when you have nobody to send.
Build the crew plan from five facts
- 1
Sort orders by certainty
Separate confirmed jobs, with survey done and advance or approval in place, from likely jobs and loose enquiries. Only confirmed jobs take a dated slot. Likely jobs get a provisional week that the farmer is told is provisional.
- 2
Estimate crew days per layout
Ask two experienced crew leaders how long recent jobs of each type took, including mainline trenching, laterals, filter and pump connection, flushing and testing. Keep their figures by job type and correct them after each season.
- 3
Subtract the lost days
Allow for moving camp, waiting for material, heavy rain, machine breakdown, rest days and return visits. A plan that assumes every day is productive is already late.
- 4
Match skills, not heads
A gang with no one who can set up filters or fault-find a pump controller cannot finish certain jobs. Mark which technicians each farm needs and sequence visits so a scarce person is not wanted in two distant places.
- 5
Replan every week
The planner, sales lead and crew leaders look at the coming weeks together. Slipped jobs are moved on the board and the farmer is called by a named person the same day.
If confirmed work exceeds capacity, choose deliberately. You can start taking orders earlier next season, bring in a vetted extra gang under your own leader, split a job into water-on and finishing visits where the design allows it, or decline. Longer-term questions, such as which skills to grow before next year, belong in workforce planning.
A one-page board for the weekly crew meeting
Farmer and village: _________
Sowing date given: __________
Order status: confirmed /
provisional
Survey and design done: y / n
Material in store: y / n
Crew days needed: ___________
Crew leader: ________________
Technician needed: __________
Planned start: ______________
Test day reserved: __________
Date promised by: ___________
Risk this week: _____________
Farmer told of change: _______Give the weekly meeting a fixed set of questions
- Which promised dates are now at risk, and who is calling each farmer today?
- What material, pump or trencher is missing for jobs starting in the coming days?
- Which gang has worked without a rest day, and when will they get one?
- Where did a finished job generate a service call, and what caused it?
- Has anyone promised a date that is not on the board?
Keep the meeting short and end it with an updated board that sales, stores and crew leaders can all see. The last question matters most in the first season. Raise unapproved promises calmly, correct them with the farmer and ask what pressure produced them. A seller rewarded only for bookings will keep making dates, so consider counting a booking fully when the job is installed and tested.
Plan the service call before it arrives
Systems commissioned in a hurry begin calling back just as crops need water. Hold some technician time unbooked in the weeks after the main installation rush, and name who answers the farmer's phone. Record each call with the job, crew, fault and fix. That list shows whether you are short of people, missing a part or repeating the same installation mistake across farms.
Protect the test
Testing is the first thing to vanish when a day runs long, and it is the step that finds a loose joint or a blocked line before it is buried or forgotten. Reserve it on the board. Require the crew leader to flush, pressurise and walk the lines, record what was seen, and show the farmer the system running. Do not pay a completion incentive on a job that has no test record, and do not blame a leader who reports that a date cannot be met safely.
Second job: give crew leaders a written site standard
Keep it to a sheet with pictures: trench depth as set by your design team, joint preparation, flushing order, filter orientation, test method, photographs required and farmer handover. Walk a finished site with each leader and agree what passes. Include the subsidy photographs and completion papers, so the gang captures them while the evidence is still visible and the office is not sending someone back.
Third job: settle camp, travel and site helpers
Before a gang leaves, name who arranges lodging, food, drinking water and transport, what the company pays and when rest falls. A leader should not discover these on arrival. Where local helpers are picked up for trenching, record each name and give a short safety talk on tools, trench edges, buried cables, heat and who to tell about an injury. If the leader cannot do that, the helper does not start.
Brief any extra gang the same way as your own. Their leader should see the standard, the test record and the safety talk before the first trench is opened.
What can wait until after planting
- Redesigning job titles across sales, design and projects.
- A scheduling application, until the paper or spreadsheet board is trusted and updated.
- Annual appraisal forms for field staff.
- A full training calendar, which is better written from the faults found this season.
Hold a review once the rush ends. Compare promised dates with actual ones, list return visits by cause and ask each crew leader what the office should have told them sooner.