The owner's monthly meeting runs through progress, billing and plant. People come up last, if at all. Two weeks later a crane signaller's certificate lapses, three jointers leave a remote camp together, and the project manager admits to not having been home since the previous milestone.
What should the monthly people review cover?
Cover five questions for each site: can the crew legally and safely do the coming work, are hours and pay accurate, is camp life acceptable, are site leaders coping, and where does everyone go next. Use named records, decide actions in the meeting and check them the following month.
Set the triggers before the meeting
A review goes wrong when each warning is debated afresh and then postponed. Agree these responses once, with site managers in the room.
- A certificate lapsing before the planned task: book renewal or name a replacement, and block the roster until proof arrives.
- Attendance sheets unsigned or entered late: the site manager names a signer for each shift and checks a sample.
- The same camp complaint twice: head office sends someone with authority to spend and reports back to residents.
- A site leader without planned leave: fix dates and appoint a deputy who can sign permits and speak to the client.
- A site entering its closing phase: speak to each person about the next posting, including honest uncertainty.
- Several exits from one crew or site: someone outside that chain talks to leavers and those who stayed.
The review sheet
Project:
Phase: mobilise / peak / close
1 PERMITS
Expiring before next review:
Crew gaps for planned tasks:
2 HOURS AND PAY
Unsigned shifts:
Pay or allowance queries open:
3 CAMP AND TRAVEL
Open complaints and age:
Rest days or home leave missed:
4 LEADERS
Who has no deputy:
5 NEXT MOVE
People with no posting named:
Exits and stated reasons:
Actions, owner, check date:Where each answer comes from
Permit data comes from the central certificate register compared with the look-ahead programme, so the planning engineer should join for that item. Hours come from signed crew sheets, device records and overtime approvals; pay queries come from accounts and the camp or site administrator. Compare a small sample of sheets with the work diary or permit log. Differences show whether records are being filled in afterwards from memory.
Camp evidence comes from the complaint log, the in-charge, medical visits and direct conversation. A quiet log proves little where the complaint goes to the person who controls rooms and rotation. Home leave and rest days come from the roster, checked against what actually happened. Manager load comes from rest taken, open approvals, client escalations and the manager's own list of what slipped.
Hold the discussion in order
- 1
Clear last month's actions
State what closed and what did not. An overdue camp repair or renewal gets a new owner or more authority, not another silent carry-over.
- 2
Start with imminent work
Check permits and cover for lifts, shutdowns, energisation, commissioning and inspections in the coming period.
- 3
Hear the exceptions
Each site lead names the biggest people risk and what they need from head office. Routine good news stays on the sheet.
- 4
Match closing sites with openings
Put planners, estimators and project managers together to compare release dates with likely demand for each role.
- 5
Confirm messages to staff
Decide who tells crews what was agreed, what was refused and what remains unknown.
Read patterns carefully
One departure after a family event says little about a site. Repeated exits after a transfer, from one camp or under one foreman deserve attention. Ask about pay, allowances, travel home, food, supervision and uncertainty about the next job, separately and without the immediate boss present. Do not label a site safe because it reports nothing. Check whether crews have stopped work for a hazard and how they were treated afterwards.
Keep personal medical details, grievance accounts and disciplinary matters out of the shared sheet. Record that a confidential case is being handled and by whom. Once the monthly routine is steady, a performance management process can link site leader objectives to permit readiness, accurate records, follow-up and developing deputies, alongside delivery and cost.
Look one phase ahead
People costs bite hardest at a project's turning points, so reserve the end of each review for them. Ask which roles the next phase adds, whether those people hold the client passes they will need, and whether camp beds, transport and induction capacity match the arrival plan. For a closing phase, ask who must stay for testing, snags, as-built records and final measurement, who can release early and what each has been told. Compare that list with tenders awaiting award, marking each possible posting as firm or uncertain. Do not let a hopeful bid appear to staff as a promised job. Where there is no next posting, plan notice, final dues, handover and return of equipment early, with advice on the rules that apply.
A worked illustration
Imagine the sheet from a water scheme in its peak phase. A pipe welder's qualification lapses before the next tie-in, two pump technicians have missed home leave, and the site manager lists no deputy. In the meeting, the planning engineer confirms the tie-in date, head office books retesting and names a cover welder from a closing site, and the owner agrees a relief technician. The manager proposes a senior foreman as deputy and sets out which approvals that person may sign. Each item leaves with an owner. The following month begins by asking whether the retest happened, whether the technicians travelled and whether the deputy has actually covered a day.
What to leave out
Leave out engagement scores without comments, combined headcount charts that hide a short crew, and lengthy staff ratings. Progress and billing belong elsewhere unless they change the people plan. If a line has not prompted a question or decision over several reviews, challenge whether it is needed. Shorter sheets get filled in honestly by tired site teams, and a gap left blank on purpose is easier to spot than one buried among dozens of fields.
Where to go next
Try the sheet on the site that is closest to a mobilisation or handover, and invite its manager to correct it. More on infrastructure and engineering contractors is on our sector page. If you want the review designed around your records, tell us your requirements.